This project is in furtherance of the study entitled Research Project on Conceptual Master Plan of Tanjung Pelepas Ecological Park (TPEP) which was completed in September 2016 for the Johor Port Authority (JPA). Memorandum of Agreement (MOA) between ISI and Johor Port Authority was signed on 19 April 2017. The project cost of RM40.0M for four years (2 April 2017- 1 April 2021).

Current Activities
  • Consultants are currently at Stage 1 working on matters concerning Kelulusan Merancang, A site visit by consultants to Tanjung Piai National Park to observe and to build a better understanding of the project. (updated October 2017)
  • Preparation of tender documents is 80% completed (updated January 2018)

  •  

    Tender documents have been completed and submitted to the client (updated August 2018)
  • The consultants are preparing new sets of tender documents based on revised project implementation schedule as requested by JPA -updated 1.10.2018