Title: Research Project on Hydrodynamic Simulation Within Port Limit of Port of Tanjung Pelepas and Establishment of Johor Port Authority (Tanjung Pelepas) Marine Data Centre (MDC)

Client: Johor Port Authority (JPA)

Project Cost: RM1.4 million

Duration: 18 months ( beginning 1 May 2015)

Status: Completed

Headed by: Assoc. Prof. Dr Mohd Zamani Ahmad

Description:

Johor Port Authority (JPA) has granted RM1.4m to ISI to undertake an 18 months study beginning 1st May 2015 with the following objectives; To perform hydrographic survey within JPA Port Limit Tanjung Pelepas; To develop a simulation model of hydrodynamic conditions of PTP water limit; To simulate pattern of hydrodynamic conditions of PTP water limit including shoreline evolution; To develop the database on hydrodynamic, hydrography and topographical data within PTP water limit.